OSHA 30-Hour Construction · Chapter 5

OSHA Cranes & Derricks Quiz — 29 CFR 1926.1400-1442 Practice (Subpart CC) — Page 4 of 4

Free OSHA 30-Hour Construction cranes and derricks practice test with 40 realistic scenarios. Operator certification, rigging inspection, power line clearance, load charts, signal person requirements, and crane assembly/disassembly with 29 CFR 1926 Subpart CC references. (Page 4 of 4)

0 / 10
Q31 / 40

A crane is making a lift near a building under construction. The load must be placed on the 5th floor, accessible only through an opening in the partially completed facade. The operator cannot see the landing point. A signal person is stationed at the landing point with a radio. As the load approaches the opening, the signal person says 'cable up... cable up... stop.' The operator stops, then the radio crackles and the operator hears 'OK, cable down.' Was this instruction valid?

Q32 / 40

A construction site crane's annual inspection certificate expired 2 weeks ago. The employer has scheduled the inspection for next week. Workers are told to keep using the crane. Is this acceptable?

Q33 / 40

A derrick is being used for stone setting on a building facade. The derrick's mast is supported by the building's steel frame. The competent person notices the mast base plate has deformed (bent) slightly under load. The mast is still plumb. What should be done?

Q34 / 40

A truck-mounted crane is set up on a road with a 3% cross-slope. The outriggers are extended but the crane is not perfectly level — the bubble level on the crane shows approximately 1.5 degrees off-level. The operator proceeds with a lift at 80% of the load chart capacity. Is this acceptable?

Q35 / 40

A multiple-crane lift is planned: two 50-ton cranes will lift a 40-ton bridge girder simultaneously. No engineer designed the lift plan. The foreman says 'each crane lifts 20 tons — they're both at 40% capacity, it's safe.' Is this acceptable?

Advertisement

Google AdSense — Responsive In-Article Ad

Q36 / 40

A crane operator is lifting a load when a sudden gust of wind causes the load to swing. The operator immediate reaction is to boom down to increase radius and stabilize the load. Is this the correct response?

Q37 / 40

A telescopic boom crane has a boom angle indicator that is reading 10 degrees lower than actual (reads 50 degrees when the boom is at 60 degrees). The operator knows this but has 'adjusted' by just adding 10 degrees mentally. Is this acceptable?

Q38 / 40

A crawler crane is being walked (traveled) up a 6-degree slope with a load. The load chart permits operation on slopes up to 5 degrees. The operator says 'it's only one more degree.' The crane has the boom facing uphill. What's the risk?

Q39 / 40

A crane's hook has been modified — the safety latch (hook keeper) has been removed because it kept getting caught on rigging. The hook itself is not twisted, cracked, or deformed. Is this hook usable?

Q40 / 40

A lattice boom crawler crane has a boom that is 200 feet long. During assembly, the crew discovers one of the 20-foot boom insert sections has a 1/4-inch deep gouge on the chord (main structural tube), approximately 2 inches long. The chord is 4-inch diameter pipe. The crew installs it anyway. Is this acceptable?