OSHA 30-Hour Construction · Chapter 3

OSHA Electrical Safety Quiz — 29 CFR 1926.400-449 Practice (Construction) — Page 1 of 4

Free OSHA 30-Hour Construction electrical safety practice test with 40 realistic scenarios. GFCI, AEGCP, temporary wiring, overhead line clearance, lockout/tagout, hazardous locations, and portable generator safety with 29 CFR 1926 Subpart K references.

0 / 10
Q1 / 40

A crew is using a portable electric hammer drill on a commercial construction site. The drill is plugged into a temporary receptacle on a 120V, 20A circuit that was installed for the job. A worker receives a mild shock when the drill's metal casing becomes energized. The circuit has a standard circuit breaker installed. What does 29 CFR 1926.404(b)(1) require?

Q2 / 40

An excavator operator is digging a trench near a marked underground electrical duct bank carrying 480V feeders to a building. The markings show the duct bank at 36 inches depth. The operator is using a 24-inch bucket. What does OSHA 1926.651(b) require before mechanical excavation near this electrical hazard?

Q3 / 40

A scissor lift is being repositioned inside a warehouse under construction. The operator raises the platform near overhead fluorescent light fixtures with exposed wiring at 277V. The top rail of the lift comes within 18 inches of the energized conductors. Is this acceptable?

Q4 / 40

A construction electrician is installing temporary wiring on a jobsite. The wiring runs along the ground through a high-traffic doorway used by material carts. What does 29 CFR 1926.405(a)(2) require for this temporary wiring installation?

Q5 / 40

A site superintendent needs to use a portable generator during the rough-in phase before permanent power is available. The generator is 5kW, 120/240V. Workers will use drills, saws, and a small welder. What grounding and GFCI requirements apply under OSHA Subpart K?

Advertisement

Google AdSense — Responsive In-Article Ad

Q6 / 40

A renovation project requires cutting into an existing wall. The foreman tells a laborer to use a reciprocating saw to cut through the drywall, saying 'the power should be off on that wall.' The laborer hits a live 120V Romex cable, causing a short circuit but no injury. What did OSHA require that the foreman failed to do?

Q7 / 40

On a jobsite, workers use multiple 100-foot extension cords daisy-chained together to reach a work area. The total run is 400 feet of 14 AWG cord powering a 15A miter saw. The saw motor runs slowly and the cord feels warm. What violations exist?

Q8 / 40

A metal extension ladder is being used by a window installer working near the service entrance of a building. The service drop conductors (120/240V, uninsulated triplex) are approximately 4 feet from the work area. The installer is on an aluminum ladder. What is the minimum safe practice?

Q9 / 40

A jobsite has been experiencing repeated GFCI tripping on a circuit powering multiple tools. The foreman tells the electrician to 'swap in a regular outlet until we finish this concrete pour.' The electrician complies. An OSHA inspector arrives two hours later. What is the violation?

Q10 / 40

Workers are using a 240V arc welder on a steel bridge project. The welder's case is metallic. The power cord is a 3-wire (2 hots + ground) SOOW cable. The ground pin on the plug has been cut off because 'the generator receptacle doesn't have a ground slot.' What does 1926.404(b)(1)(iii) require regarding equipment grounding?