OSHA 30-Hour Construction · Chapter 2

OSHA Scaffold Safety Quiz — 29 CFR 1926.450-454 Practice Questions — Page 1 of 4

Free OSHA 30-Hour Construction scaffold safety practice test with 40 realistic scenarios. Covers supported scaffolds, suspended scaffolds, aerial lifts, platform construction, guardrails, and competent person inspection with 29 CFR 1926 Subpart L references.

0 / 10
Q1 / 40

A mason is working from a tubular welded frame scaffold 3 tiers high, approximately 18 feet above grade. The scaffold has no guardrails on the inner face because bricks are being stacked on the platform and the mason claims guardrails would interfere with the work. Is this compliant?

Q2 / 40

A scaffold erector is building a supported scaffold. The base plates are set directly on asphalt pavement. The scaffold will reach 40 feet in height. What does 29 CFR 1926.451(c)(2) require for the foundation?

Q3 / 40

During disassembly of a suspended scaffold at a high-rise window washing project, a worker discovers the wire rope has a broken strand with 4 of its 19 wires broken over a 12-inch section. The worker's supervisor says to finish the job and replace the rope afterward. What should happen?

Q4 / 40

A medium-duty scaffold (50 psf rated) is being loaded with masonry blocks. The foreman calculates the total weight of blocks plus workers as 52 psf. The scaffold manufacturer's rated capacity is 50 psf or 1,250 lbs total. The foreman argues it's 'close enough.' What does OSHA require?

Q5 / 40

On a two-point suspension scaffold (swing stage), two window installers are working at the 12th floor. The scaffold platform is 32 inches wide. What fall protection is required for each worker?

Advertisement

Google AdSense — Responsive In-Article Ad

Q6 / 40

A competent person inspects a supported scaffold at the start of the shift and finds the cross-bracing is missing a locking pin on the third tier. The competent person tells workers to start using the scaffold while he goes to get a replacement pin. Is this acceptable?

Q7 / 40

Workers access a scaffold platform by climbing the cross-braces. The scaffold is 25 feet high. The site superintendent says, 'That's how we always do it.' What does OSHA 1926.451(e) require for scaffold access?

Q8 / 40

A supported scaffold 30 feet high and 5 feet wide (single bay) is erected adjacent to a building but is not yet tied to the structure. Workers notice the scaffold swaying in a 15 mph wind. What does the standard require?

Q9 / 40

A scaffold is erected directly under an active 7,200-volt overhead power line. The minimum clearance distance from the scaffold to the line is measured at 2.5 feet. Workers are installing siding from the scaffold. Is this compliant?

Q10 / 40

A tube and coupler scaffold is erected by a crew. The qualified person's design called for specific coupler torque values and placement patterns. During inspection, the competent person finds several couplers have been tightened by hand only ('snug tight' but not torqued). What is the correct action?