OSHA 30-Hour Construction · Chapter 2

OSHA Scaffold Safety Quiz — 29 CFR 1926.450-454 Practice Questions — Page 2 of 4

Free OSHA 30-Hour Construction scaffold safety practice test with 40 realistic scenarios. Covers supported scaffolds, suspended scaffolds, aerial lifts, platform construction, guardrails, and competent person inspection with 29 CFR 1926 Subpart L references. (Page 2 of 4)

0 / 10
Q11 / 40

A mason is working from a tubular welded frame scaffold that is 3 tiers high (approximately 18 feet). The scaffold has no guardrails because the mason claims 'guardrails get in the way of laying brick.' The scaffold is fully planked and has proper access. What is the violation?

Q12 / 40

A scissor lift is being used to install ceiling fixtures at 28 feet inside a warehouse. The worker on the platform is not wearing a harness. The lift has standard guardrails (top rail at 42 inches, midrail at 21 inches, toeboard). Is the worker required to wear a PFAS?

Q13 / 40

A two-point suspension scaffold (swing stage) is set up at the 15th floor of a high-rise. The platform is 24 feet long with two workers. The supporting wire ropes have a safety factor of 6. The rigger attached the stirrups directly to the platform — no additional fasteners. What is wrong?

Q14 / 40

A supported scaffold 4 tiers high (about 24 feet) is erected next to a masonry building under construction. The scaffold is NOT tied to the building. The competent person says 'it's heavy enough — it won't tip.' The base plates are on compacted gravel. Is this compliant?

Q15 / 40

A competent person is inspecting tubular welded frame scaffolds at the start of the shift. One scaffold leg shows a 2-inch dent from a forklift impact. The dent is about 1/4 of the tube diameter deep. The foreman says 'it's just cosmetic.' What must be done?

Advertisement

Google AdSense — Responsive In-Article Ad

Q16 / 40

A crew is disassembling a supported scaffold. Workers are passing frames down hand-to-hand from the 3rd tier. The frames are being stacked on the ground but not secured. A gust of wind knocks over two stacked frames, nearly striking a worker. What safety practice was violated?

Q17 / 40

An employer uses a tubular welded frame scaffold rated as 'light duty' (25 psf). Workers are doing drywall finishing from the scaffold — one worker, plus a stack of 10 drywall sheets (4×8 ft, approx 55 lbs each) being stored on the platform. The scaffold platform is 3 feet × 7 feet. What is the loading concern?

Q18 / 40

A suspended scaffold (swing stage) has counterweights on the outrigger beams consisting of standard concrete blocks (8×8×16 inches, approximately 36 lbs each). The manufacturer specifies a 4:1 safety factor for counterweights and calls for 1,200 lbs of counterweight. The rigger uses 30 blocks (30 × 36 = 1,080 lbs). Is this acceptable?

Q19 / 40

Workers on a supported scaffold access the platform by climbing the cross-braces. The scaffold is equipped with a built-in ladder on one end, but it's at the far end from where workers are working. A compliance officer observes workers climbing the cross-braces. What is the citation?

Q20 / 40

A boom lift (articulating boom) is being operated on a 5-degree slope. The manufacturer's operator manual states the maximum allowable slope is 3 degrees. The slope indicator on the lift reads 4 degrees. The operator levels the platform using the platform tilt function and continues work. Is this acceptable?