OSHA 30-Hour Construction · Chapter 5

OSHA Cranes & Derricks Quiz — 29 CFR 1926.1400-1442 Practice (Subpart CC) — Page 2 of 4

Free OSHA 30-Hour Construction cranes and derricks practice test with 40 realistic scenarios. Operator certification, rigging inspection, power line clearance, load charts, signal person requirements, and crane assembly/disassembly with 29 CFR 1926 Subpart CC references. (Page 2 of 4)

0 / 10
Q11 / 40

A 50-ton hydraulic crane is set up with outriggers fully extended on asphalt. The outrigger pads are 2-foot square steel plates. The ground pressure under one outrigger during a near-capacity lift is calculated at 85 psi. The asphalt is 3 inches thick on compacted base. Is this setup adequate?

Q12 / 40

A mobile crane is working 30 feet from an energized 115 kV transmission line. The operator plans a lift where the boom tip could come within 18 feet of the line. What is the minimum clearance required under 1926.1408 Table A?

Q13 / 40

During assembly of a tower crane, the crew discovers a wire rope sling with 8 randomly distributed broken wires in one strand, within one lay length. The sling is 3/4-inch diameter, 6×19 classification. Is the sling usable?

Q14 / 40

A crane operator is making a blind lift — the load is on the other side of a building, out of the operator's view. A signal person with a radio provides directions. The radio battery dies mid-lift. The operator loses communication. What must the operator do?

Q15 / 40

A lattice-boom crawler crane is traveling with an 8,000-lb load suspended, on firm level ground. The track is 12 feet wide. The operator is traveling at a normal walking speed. Workers are walking alongside the load to steady it. Is this compliant?

Advertisement

Google AdSense — Responsive In-Article Ad

Q16 / 40

A rigger attaches two 5/8-inch wire rope slings to a 6,000-lb steel beam using a vertical hitch configuration (each sling straight up from the load to the hook). The sling's rated capacity in a vertical hitch is 6,200 lbs each. The sling angle is 0 degrees (vertical). Is the lift acceptable?

Q17 / 40

A crane operator arrives Monday morning. The crane has been parked on-site over the weekend with the boom lowered. The operator does a walk-around visual check but skips the operational checks (function test of all controls, LMI test, anti two-block test) because 'it worked fine Friday.' Is this compliant?

Q18 / 40

During a lift, a crane's load moment indicator (LMI) alarm sounds, warning of an impending overload. The operator pauses, checks the load chart, and realizes the lift is at 98% of capacity at this radius. The foreman says 'just bump it up — it's only for a minute.' What must the operator do?

Q19 / 40

A tower crane is erected on a construction site adjacent to a public sidewalk. There is no overhead protection for pedestrians. During a lift, the load will at one point pass over the sidewalk. Is this permitted?

Q20 / 40

A signal person is directing a crane operator using hand signals during a critical lift. The signal is 'boom up, load up, swing right' — a complex multi-function signal. The operator sees the signal but hesitates. The signal person repeats the signal more aggressively. What is the correct protocol?