OSHA 30-Hour Construction · Chapter 5

OSHA Cranes & Derricks Quiz — 29 CFR 1926.1400-1442 Practice (Subpart CC) — Page 1 of 4

Free OSHA 30-Hour Construction cranes and derricks practice test with 40 realistic scenarios. Operator certification, rigging inspection, power line clearance, load charts, signal person requirements, and crane assembly/disassembly with 29 CFR 1926 Subpart CC references.

0 / 10
Q1 / 40

A 50-ton hydraulic crane is being set up on a construction site. The outriggers are fully extended. The crane will lift a 12,000-lb HVAC unit at a 40-foot radius. The operator checks the load chart and sees the maximum capacity at 40 feet is 14,500 lbs on outriggers. The rigging weighs 800 lbs. Is this lift within the crane's rated capacity?

Q2 / 40

A mobile crane is working 30 feet from an energized 115 kV overhead transmission line. The operator claims he only needs to maintain 10 feet of clearance because 'that's the OSHA minimum.' What is the actual minimum clearance required by 1926.1408 Table A for this voltage?

Q3 / 40

During assembly of a tower crane, the crew discovers a wire rope sling with 8 randomly distributed broken wires in one rope lay. The sling is a 6×19 IWRC rope being used to lift tower sections. The crew lead says to use it anyway because 'we have a safety factor.' What does 1926.1414(b) require?

Q4 / 40

A crane operator is making a blind lift — the load is on the other side of a building, out of the operator's direct line of sight. The operator can see the rigger through a gap in the structure but not the load itself. What does OSHA 1926.1419 require?

Q5 / 40

A lattice-boom crawler crane is traveling with an 8,000-lb load suspended. The track is on firm, level ground. The operator is moving at approximately 1.5 mph. Under 1926.1417(n), is this acceptable?

Advertisement

Google AdSense — Responsive In-Article Ad

Q6 / 40

A rigger attaches two 5/8-inch wire rope slings to a 6,000-lb steel beam using a vertical hitch configuration. Each sling has a vertical-rated capacity of 5,800 lbs. The rigger does not use a tagline because 'the beam is heavy enough not to swing.' What issues exist?

Q7 / 40

A crane operator arrives at the jobsite Monday morning. The crane has been parked on-site over the weekend. The operator does a walk-around and starts the engine. Before making the first lift of the day, what does OSHA 1926.1412(d) require?

Q8 / 40

During a lift, a crane's load moment indicator (LMI) alarm sounds, warning of an impending overload. The operator looks at the load, estimates it's within limits based on experience, and manually overrides the LMI to continue the lift. Two minutes later, the crane tips. What section of 1926 Subpart CC was violated?

Q9 / 40

A tower crane is erected on a construction site adjacent to a public sidewalk. There is no overhead protection for pedestrians. Under 1926.1424, what protections are required for the public area?

Q10 / 40

A signal person is directing a crane operator using hand signals. The crane is making a critical lift of a 20,000-lb chiller unit being placed on a 5th-floor mechanical room. The operator momentarily loses sight of the signal person when the load passes behind a column. What must happen?