OSHA 30-Hour Construction · Chapter 3

OSHA Electrical Safety Quiz — 29 CFR 1926.400-449 Practice (Construction) — Page 2 of 4

Free OSHA 30-Hour Construction electrical safety practice test with 40 realistic scenarios. GFCI, AEGCP, temporary wiring, overhead line clearance, lockout/tagout, hazardous locations, and portable generator safety with 29 CFR 1926 Subpart K references. (Page 2 of 4)

0 / 10
Q11 / 40

A construction site uses portable generators for temporary power. A worker plugs a circular saw directly into a generator's 120V outlet. The generator is not equipped with GFCI protection. The worker is standing on damp concrete. What is required?

Q12 / 40

An excavator operator is digging near a utility marking that says 'UNDERGROUND ELECTRIC — 13.2 kV.' The one-call center marked the line, but the marks are 3 days old and partially faded. The operator starts digging 3 feet from the faded marks. The bucket strikes the cable. What should have been done?

Q13 / 40

A construction electrician installs temporary wiring for job-site lighting. The wiring is type NM (Romex) cable run along the surface of studs at 6 feet height, secured every 6 feet with staples. The run is 40 feet long, powering 4 LED temporary lights. Is this compliant?

Q14 / 40

A crew working on a highway lighting project is replacing a pole-mounted light fixture near an active 7,200V overhead power line. The crew uses a metal extension ladder. The nearest energized conductor is 4 feet horizontally from the work position. What clearance must be maintained?

Q15 / 40

A jobsite has been experiencing repeated nuisance tripping of a GFCI on a circuit powering a worm-drive circular saw. The foreman instructs a worker to replace the GFCI outlet with a standard outlet 'just for today' until a new GFCI can be installed. Is this acceptable?

Advertisement

Google AdSense — Responsive In-Article Ad

Q16 / 40

An electrician is working on a 480V panelboard, replacing a circuit breaker. The electrician turns off the main breaker but does not verify zero voltage, lock out, or tag it. Another worker turns the main back on. The electrician is shocked. What LOTO violations occurred?

Q17 / 40

On a bridge renovation project, workers are cutting rebar with an electric grinder. The grinder's 3-prong plug has the ground pin broken off. The tool is plugged into a GFCI-protected extension cord. Is this acceptable?

Q18 / 40

A temporary service (power pole) is installed on a construction site. The panel is mounted on a wood post at 72 inches above grade. The panel door is missing — breakers are exposed to weather. Workers plug in tools at this panel daily. It has rained. What violations?

Q19 / 40

A construction crew is using multiple 100-foot extension cords daisy-chained to power tools 400 feet from the nearest outlet. The cords are 14-gauge, rated for 15A. The total connected load is 13A. What are the concerns?

Q20 / 40

On a construction site, a metal junction box for temporary power is mounted on a metal stud wall. The box is energized (has live wires inside) but the box itself is not grounded. The circuit does have GFCI protection. A worker touches the box while standing on wet ground and receives a shock. Why?