OSHA 30-Hour Construction · Chapter 3

OSHA Electrical Safety Quiz — 29 CFR 1926.400-449 Practice (Construction) — Page 3 of 4

Free OSHA 30-Hour Construction electrical safety practice test with 40 realistic scenarios. GFCI, AEGCP, temporary wiring, overhead line clearance, lockout/tagout, hazardous locations, and portable generator safety with 29 CFR 1926 Subpart K references. (Page 3 of 4)

0 / 10
Q21 / 40

A portable generator (5kW) is being used to power tools during the framing phase. The generator does NOT have GFCI outlets. Instead, the employer implements an Assured Equipment Grounding Conductor Program (AEGCP). What does the AEGCP require?

Q22 / 40

A scissor lift is being repositioned inside a warehouse with exposed overhead bus bars at 480V, 20 feet above the floor. The lift's platform, when raised, reaches 19 feet. The operator raises the platform to adjust a light fixture 2 feet horizontally from the bus bars. What clearance is required?

Q23 / 40

A worker using a portable circular saw notices the blade guard is sticking. The worker continues using the saw, holding the guard open manually when needed. Is this a violation?

Q24 / 40

A construction electrician is installing a temporary light string for job-site illumination. The string has 10 Edison-base sockets with bare bulbs, hung at 9 feet above the floor along a hallway where workers carry sheetrock. Is this compliant?

Q25 / 40

A warehouse renovation requires cutting into an existing wall. The foreman tells a laborer to use a reciprocating saw to cut a 2×4-foot opening. The laborer does not know what is inside the wall. There is a live 120V circuit 6 inches behind the drywall. The saw blade contacts the cable, causing a short and flash. What should have been done?

Advertisement

Google AdSense — Responsive In-Article Ad

Q26 / 40

Workers are using a 240V arc welder on a steel bridge project. The welder's metallic case has a 3-prong plug. During welding, a ground fault inside the welder energizes the case. A worker leaning against the bridge steel touches the welder case. What protection does the worker have?

Q27 / 40

A job-site temporary power pole has a 200A main breaker feeding multiple 20A receptacle circuits. One worker replaces a 20A breaker with a 30A breaker 'to stop the tripping.' The wiring is 12-gauge (rated for 20A). What is the hazard?

Q28 / 40

An electrician is working on energized 277/480V bus bars with insulated tools, wearing no arc-flash PPE other than safety glasses. The electrician is a licensed journeyman. Is this compliant with OSHA?

Q29 / 40

A construction worker is using a hammer drill outdoors on a bridge deck. The drill has a 3-prong plug and the worker is using a 50-foot, 14-gauge extension cord labeled for 'indoor use only.' It has recently rained. Is the extension cord acceptable?

Q30 / 40

On a multi-story construction project, temporary wiring for upper floors is run through a 12-inch × 12-inch floor opening. The cables contact the concrete edge. Workers step near this hole regularly. What protection is required?