OSHA 30-Hour Construction · Chapter 4

OSHA Excavation & Trenching Quiz — 29 CFR 1926.650-652 Practice Questions — Page 4 of 4

Free OSHA 30-Hour Construction excavation and trenching practice test with 40 realistic scenarios. Soil classification, protective systems, spoil piles, access/egress, competent person duties, hazardous atmospheres with 29 CFR 1926 Subpart P references. (Page 4 of 4)

0 / 10
Q31 / 40

A competent person uses a pocket penetrometer reading 1.2 tsf on cohesive clay and classifies it as Type A. No other tests were done. Is this classification defensible?

Q32 / 40

After a 3-inch rainstorm, a 12-foot trench in Type B soil with hydraulic shoring has 2 feet of water. The competent person plans to pump it out and resume work 1 hour later without adjusting the shoring. Is this sufficient?

Q33 / 40

A trench in Type B soil is open for 3 weeks. After 1 week of hot dry weather, tension cracks appear 3 feet from the edge. Hydraulic shoring pressure has dropped 20%. Workers continue. What must happen?

Q34 / 40

How many cubic yards of soil must collapse to cause a fatal cave-in?

Q35 / 40

A benching system for a 16-foot excavation in Type A soil uses Appendix B Figure B-1. After 4 days, vertical bench faces are spalling (peeling). The soil appears drier. What is happening?

Advertisement

Google AdSense — Responsive In-Article Ad

Q36 / 40

A worker is in a 6-foot trench kneeling to make a pipe connection. Their hard hat falls and rolls outside the trench box. They crawl out of the box for a moment to retrieve it. Is this 10-second exposure outside the box acceptable?

Q37 / 40

A contractor digging a 5-foot trench for a water line decides no protective system is needed because it's 'only 5 feet deep.' Is this correct?

Q38 / 40

A crew is digging a 12-foot-deep trench in Type B soil. The trench runs parallel to a busy highway, and vibrations from traffic are noticeable. The competent person classified the soil as Type B based on one manual test. What additional protective measure is required?

Q39 / 40

An excavation is 5 feet deep in stable rock. The competent person inspects it at the start of the shift and finds no issues. A rainstorm passes through at 10 AM but the trench appears dry. When must the next inspection occur?

Q40 / 40

A 6-foot deep trench in Type C soil is being excavated near an existing underground fiber optic line. The one-call center marked the line, but the exact depth is uncertain. The operator begins digging within 2 feet of the marking using a backhoe. Is this compliant?